Cable Condition Assessment in a 40 MW Solar Plant.

UHF partial discharge testing for a Gujarat power utility after a cable failure caused a long outage.

Sector
Solar, BESS & Power Generation
Service
Testing & Commissioning
Year
2023
Location
Gujarat, India
Client
Power utility

The Situation.

A cable failure in a 40 MW solar plant caused a long outage. The utility needed to know the condition of the remaining cables before more failed.

What We Did.

  1. UHF partial discharge testing of cable terminations and joints
  2. Identified locations showing partial discharge activity
  3. Reported findings with recommended actions

The Result.

  • Cable condition assessed across the plant
  • Defects located so they could be repaired before failure

Facing Something Similar?

Tell us the asset, the location and the stage. We'll share comparable work and a proposed scope.

Enquire Now



This will close in 0 seconds

Enquire Now


    This will close in 0 seconds

    Submit


      This will close in 0 seconds

      Enquire Now


      This will close in 0 seconds

      Enquire Now last



      This will close in 0 seconds

        This will close in 20 seconds

        New contact us form
        Subscribe For

        This will close in 0 seconds

        This will close in 0 seconds

          This will close in 0 seconds

          Cookie Consent Banner by Real Cookie Banner